A black and white head shot of Mathias Cormann, who is smiling and wearing a dark jacket, shirt and tie.

Senator the Hon Mathias Cormann

Minister for Finance

18 September 2013 to 30 October 2020

Implementing the Coalition's Broadband Policy

JOINT MEDIA RELEASE

Senator the Hon. Mathias Cormann
Minister for Finance

Hon. Malcolm Turnbull MP
Minister for Communications

Date

The Coalition Government is committed to completing the National Broadband Network sooner, more affordably for consumers and at less expense to taxpayers.

NBN Co’s shareholder ministers – Communications Minister Malcolm Turnbull and Finance Minister Senator Mathias Cormann – have today issued an interim Statement of Expectations to the company as the first step in implementing changes to Government policy.

The interim Statement will guide NBN Co’s construction and operational activities pending changes to the Board and while a Strategic Review and Independent Audit of the project is carried out and a new NBN Co Corporate Plan is drafted.

The interim Statement instructs NBN Co to continue to roll out the network as rapidly and cost-effectively as possible throughout this process.

In the short term, the interim Statement will see the NBN Co meet its contractual obligations by continuing to roll out fibre to the premises while the company conducts the strategic review of the project.

The NBN Co has recently advised the Government that is proposing to revise its roll out target for premises passed by fibre by 30 June 2014 down by almost half from the forecast made six months ago.

The interim Statement provides NBN Co with the flexibility to use a wider range of technologies to connect businesses and homes to the network.  For example, this will allow NBN Co to trial the latest VDSL technology to deliver super fast broadband to homes and businesses in multi dwelling units such as apartment blocks.

A key priority will be to reduce the backlog of 66,000 premises passed by the NBN fibre network which cannot currently obtain service.  This includes the majority of apartments, schools and businesses in areas where the fibre network has been rolled out.

Under the interim Statement of Expectations, construction will be completed in areas containing 300,000 premises where construction contracts have been signed.

Detailed network design work is underway in areas containing a further 645,000 premises.  In geographic areas where NBN Co is in a position to hand over final designs to construction partners, some of these sites may see construction work begin shortly.

There are also more than 900,000 premises listed on the one year roll out plan on the NBN Co website where only preliminary network design work is underway.  Decisions about actual construction in these areas will be taken after the reviews into the NBN rollout are completed.

These decisions will ensure there is a steady flow of work on the NBN until well into 2014.  This will provide certainty for contractors and ensure they do not have to demobilise work forces.

We expect this period of review will lead to revisions to the timing of the roll out and to updated forecasts.

It is important to bear in mind however that the NBN roll out has, to date, repeatedly missed its targets.

It is our goal following the completion of the review and a new corporate plan to see the NBN Co set realistic roll out targets and then consistently deliver on them.

TABLE: Revised NBN Forecasts
Total Premises Forecast to be Passed by Fibre (’000)

 30/06/201230/06/201330/06/201430/06/201530/06/2016
Corporate Plan, Dec 20103171,2682,7114,1735,647
Corporate Plan, Aug 201239 (actual)3411,3072,9124,625
Draft Corporate Plan, Jun 2013 208 (actual)9812,4503,943
NBN Revised Forecast, Sep 2013  7291,7403,115
Note: 'passed' includes 'service class zero' premises which cannot obtain service